Custom Data Date Support allows users to select a specific Data Date for scheduling, rather than being restricted to the system default (today’s date at 8:00 AM).
This enhancement enables teams to simulate different project timelines, analyze progress against historical or future checkpoints, and make informed corrective decisions to improve project delivery.
The Data Date is the reference date used by the scheduling engine to:
Previously, the system automatically used today’s date at 8:00 AM as the Data Date. With this feature, users can now manually select the desired Data Date.
To use a custom Data Date, follow the steps given below.
Go to a Project, open the Schedules Module

Open a created Schedule

Click on Configuration

Under General, select the desired date and time

When the Date is updated successfully, a success toast is shown.

In Gantt, click Schedule Now

The system will now use the selected Data Date instead of the system’s current date.