Instructions
Those Contracts in which Schedules are attached, in those Contract Forms, if there is a Task preset section, Tasks can be added.
To link the task to the Progress Update forms or the Inspection forms, follow these steps
- You can add a task by clicking on the Add Tasks button

- Upon adding a task, select the task, and the details of the task, which need to be filled, will appear. Actual Start Date -
Actual End Date -
Progress -
Remaining Duration -
These can be edited by clicking on the icon highlighted below.

- Fill the data


- The linked BOQ items can also be updated, select the BOQ item which needs to be updated

- Click on the edit icon as shown below

- Update the item and Confirm

- The BOQ item will get updated and the Task (which contains BOQ items) is linked to an Inspection Form.